Structural project construction FROM A TO Z
Structural project construction FROM A TO Z
1. 1. Introduction
In this project, you will learn all the steps of construction of “Chamsine Bakery” starting from the soil tests and site excavation to the construction of the slabs. During any construction project, you will face many problems and
learn how to think in a smart way to find the best solution to all these
problems.
· Presentation of
the project:
It is a construction of 2 buildings:
The first one (Block A) has 3 floors + 1 roof.
The second one (Block B) has 2 floors + 1 roof
+ 1underground.
·
Project
location: The project is located in Tripoli, north of Lebanon, Kalamoun highway
(Kal 1692) (Fig.1, fig.2).
Figure 1: 3D view of the project
Figure 2: 3d view 2 of the project.
·
First, take the drawing from the architect.
Figure 3: Cad drawing from an architect.
·
Then draw, using AutoCAD, the columns and the beams that should be
built up.
· The next step is to import the modified cad file (fig.4) and all the given data into the "ETABS" software then export each slab to the “SAFE” software to obtain the reinforcement in each structural element (fig.5). You can see the "Structural Project" blog post, for more information about structural analysis.
Figure 4:
Modified cad file containing only the columns and beams.
Figure 5:
Safe file.
Figure 6: Site excavation. You can see the high depth of excavation because there is an underground in block B. You can also see the good strata (Hight strength soil).
2. Site investigation and excavation:
2.1.Soil tests were made before
starting the excavation, at Sana Engineer in Beirut, and the results were: good soil type.
2.2. A surveying engineer
was responsible to:
- Take
the borders and specify the limitation points of the building.
- Plot the points of excavation on the
ground.
- Take the level of the road and of the ground and make them of the same level in blocks A and B.
2.3. Take the underground level in block B.
2.4. Excavation:
- In block B: excavation of
the underground that is = 530 cm = 5.35 m (underground floor = 4.8m = 480cm +
mat foundation = 45cm + cleanness concrete layer = 10cm) and 1m more than the
borders of the underground from left and right in 4 sides.
- In block A: footing excavation = 115cm (footing
depth=50cm + 40cm tie beam + 15cm floor + cleanness concrete layer=10cm)
Figure
7: Mat reinforcement
and dowels reinforcement…
You can see in this figure that
the mat reinforcement is 2-way steel, top, and bottom, 14mm
diameter, and it is above the ground of a concrete cover = 50 mm. This steel is
put after casting a 10 mm cleanness concrete. You can also see the blue waterproof
that is between the 2 reinforcement bars of the wall.
Figure
8: Mat foundation and waterproof in the underground of
block B. You can see in this figure the wood contour that
must be done for safety and to specify the boundary that should be cast.
Figure
9: The connection between the elevator and the strip footing.
Figure
10: Waterproof between wall and strip footing reinforcement.
Figure
11: Stairs
reinforcement in the strip footing.
Figure
12: Column reinforcement in strip footing (Block B). You can
see the spacers of 5 cm that allow a good concrete cover, and the seats that allow
spacing between top and bottom steel layers.
Figure
13: Soil fill after the concrete curing of the foundation in block A.
Figure 14: The soil fill depth should covers the
column neck.
Figure
15: Soil fills after concrete curing in the footing. We can
see the column reinforcements that are ready to be put in the column place in
the next step.
Figure
16: Tie beam. It will be cast after soil fill. Then fill
the voids with soil before casting the floor.
Figure
17: New continuous footings in block A. These footings are
done after casting all the other footings, because of a modification in the
construction after that the contractor
decided to remove a column from block A due to architectural causes.
Figure
18: New footings in the same place as the casted footings to
increase the capacity of the columns.
Figure
19: Tie beam in the footing.
Figure 20:
The beginning of casting the continuous footings.
Figure
21: Continuous footing in block A ,after removing the middle column, to
increase the capacity of the other columns.
Figure 22: Casting the underground floor.
3. Steps of construction:
3.1. The first step is the cleanness concrete layer = 10 cm
in blocks A and B
3.2. 2nd step: axis of columns in blocks A and B
3.3. 3rd step: Foundation reinforcement:
§ In block A: isolated footing, use 2-way bottom steel.
§ And mat foundation in block B is 2-way steel, top and bottom of 14mm diameter.
You can see a comparision between the mat foundation and the isolated foundation in the "Footing design" blog post.
Figure 23: Shear wall reinforcement in block B.
3.5. Add retaining walls along the contour of the underground
of block B because the soil is around the building. These walls have a
height of 4.8m= height of underground. They are subjected to soil load from the
outside and are connected to the slab at the top (simply supported) and to the
strip foundation at the bottom (fixed). So the main reinforcement is on the
inside (in the side of the building not on the side of the soil) and add also
reinforcement at support using fixed connection because of the negative
moment.
3.6. Add shear walls in blocks A and B on the perimeter of
the elevator.
3.7. The column reinforcements are calculated using
“Etabs”. And the slab reinforcements are calculated using “Safe”. All the
columns are square so use square foundations for isolated footings in block A.
3.8. When putting the column reinforcements in their place,
the column must be vertical so it should be leveled using the suitable tool
containing mercury.
3.9. Put each column in its place then put a wood cover to cast the columns.
4. Types of slabs:
a. In block A, and because of removing a column from the middle, there is a large span, so use the post-tension 2-way solid slab to have a small beam section with a big capacity.
Post-tensioning is done onsite by installing post-tensioning tendons within the concrete form-work in the same method of installing rebar, then tension the bars using a special tool (Fig. 27).
When the steel is tensioned before concrete placement, the process is called pre-tensioning. When the steel is tensioned after concrete placement, the process is called post-tensioning.
The main advantages of post-tensioned reinforced concrete slab are:
- Increasing clear spans.
- Thinner slabs.
- Lighter structures.
- Reducing cracking and deflections.
- Reducing story height.
- Rapid construction.
Figure
24: Post tension cover steel.
Figure
25: Post tension steel.
Figure
26: 2-way post-tension slab.
Figure
27: Tensioning the steel.
Figure 28: 1-way ribbed
slab in block B.
Figure
29: Last photo taken for block A.
Figure 30:
Last photo taken for block B.
5.
Conclusion:
This project is one of the best and most
important experiences in which you can learn how to deal with new problems, and
how to use your known information correctly to solve all the
difficulties. And to be a good and special engineer you have to follow new
projects to gain as much as possible of experiences.
Comments
Post a Comment